Project description

GBA (Gross Building Area) 5783.00 m2
NUA (NET USABLE AREA) 5622.67 m2
73 rooms, congress hall, wellness centre, glass porch and outdoor swimming pool

The construction works took only 8 months. Due to weak foundations, the walls and the ceilings of the extension have been executed in light materials (Ytong). The existing stone walls have been undercut and a glass porch with green roof was constructed. The west wing and the entire fourth floor have been expanded. There have been constant architect’s interventions during the execution process.


Investors

Potestas d.o.o.


Financial value

58 mil. HRK / 7,7 mil. EUR